|
Hartsfield-Jackson Begins $215 Million
Baggage Screening Project
Hartsfield-Jackson Atlanta International Airport began constructing
the Transportation Security Administration's in-line baggage
screening facilities near the north and south terminals in
July. A special government-airport partnership will make the
federally mandated TSA Baggage Screening Project a reality
at an estimated cost of $215 million.
Constructed in two phases, the two underground facilities,
one each at the North and South Terminals, are being built
to accommodate the electronic security screening of checked
baggage. Airport representatives expect construction of both
phases to be completed within 12 to15 months.
The north terminal facility will encompass roughly 67,000
sq. ft. while the south terminal will total approximately
54,000 sq. ft. Each screening area will be constructed underneath
the upper level curbside entrance points of both terminals.
Aviation officials anticipate the electronic screening devices
being in full operation by the fourth quarter of 2005.
Value of Georgia's June Contracts Up by
30 Percent
The value of contracts for future construction in the state
of Georgia increased by 30 percent in June, compared to the
same period of a year ago, McGraw-Hill Construction reported.
All sectors experienced double-digit increases, led by the
nonbuilding sector's 84 percent uptick. Overall, contracts
for the month totaled roughly $2.25 billion, or about $500
million ahead of last June's pace.
The nonbuilding sector again was the greatest percentage
gainer, improving by 84 percent over last June to end up at
$444.7 million. Residential moved up by 18 percent to total
nearly $1.2 billion for the month. Nonresidential improved
by 28 percent from a year ago to total approximately $652.6
million.
For the year-to-date, Georgia activity is 21 percent ahead
of 2003's pace. Residential is 24 percent ahead of the first
six months of 2003, with approximately $7.2 billion reported
so far. The second-largest market, nonresidential, is now
13 percent ahead of a year ago, with roughly $2.9 billion
of contract value reported to date. Nonbuilding is 26 percent
ahead year-to-date, with a nearly $1.5 billion total.
Clark Design/Build Team Awarded $73.6M
Contract at Fort Stewart, Ga.
Clark Design/Build of Tampa was awarded a $73.6 million
emergency funded contract on May 25, 2004, by the U.S. Army
Corps of Engineers' Savannah District for the design, total
site development and construction of a modular barracks campus,
laundry facilities, battalion headquarters, company operations,
arms vaults and vehicle maintenance facilities at Ft. Stewart,
Ga. Three battalions and 852 soldiers of the 4th Brigade,
U.S. Army 3rd Infantry Division will use this facility.
This design/build project must be completed in 142 days and
includes a first occupancy milestone target of just 77 days
for barracks, laundry, battalion headquarters and company
operations buildings to service the first 240 soldiers. "This
is the most aggressive schedule I've encountered in my 24
years with Clark," said Dave Young, Clark's onsite construction
executive and vice president for the project.
Approximately 102 acres of previously forested area was cleared
and grubbed in only eight days, and within two weeks, more
than 16,000 sq. ft. of modular office space was completely
operational for use by the staff of Clark Design/Build, the
USACE personnel and the project's key subcontractors.
The design workshop sessions that defined all site grading,
utilities, building components and approved design were completed
in only two weeks with construction drawings issued 29 days
from contract award.
Despite rainy conditions during the first 30 days, the work
has proceeded on schedule. The first of 142 custom barracks
modular buildings were delivered on June 30, 2004, 20 days
after the design layout and construction requirements were
approved.
"This will be the first project built to house a combat
ready unit that will improve on the Army's already rapid deployment,"
said Colonel Michael W. Biering, director of Public Works
at Ft. Stewart.
Clark Construction Group of Tampa is the acting general contractor
and design/build coordinator for the project. LS3P Associates
Limited of Charleston, S.C. is the lead designer.
Shaw Group Wins Part of $200 Million City
of Atlanta A/E Services Contract
The Shaw Group, Baton Rouge, La., recently announced that
Shaw/AIM JV, a joint venture of Shaw Environmental and AIM
Partners was awarded a contract by the City of Atlanta to
provide engineering and construction management services for
various departments within the municipality. The contract
will support the city's architectural and engineering needs,
including the recently announced $3.3 billion sewer rehabilitation
effort. Shaw/AIM JV was one of six companies selected under
this contract, which has a potential shared value of over
$200 million.
Shaw/AIM JV is the prime contractor in a teaming arrangement
with Applied Engineering & Science; Bench Mark Management
LLC; Cheeks/Hornbein Architects; Environmental Resource Services;
Neil Engineering; Precision Engineering & Surveying; The
Mosby Law Group; and Washington Group International.
|